Sunday, 30 March 2014

Painting

Went to site this morning, painters there ,4 of them,,yay,,they are doing the outside today and tomorrow starting the internal spraying,,all of the window frames are painted,,the portico and el fresco are finished,,talking to the guys, they said with no delays  ie not getting pulled off this job , they should b finished by the end of the week,goodo,here are todays pics





Saturday, 29 March 2014

Painting Begins

Went to site friday morning, the plumber was there hooking up our rain water tank,but no painters ,,,went to the site friday arvo with hubby, painters have been there, all doors off,all window sills painted and the wet rooms have had a coat as well,so didnt expect that,ceilings havnt been started yet, so Monday must b the day its all going to start happening,hope there is more than 1 painter,,.,hopefully it will only take a week, but who knows,sorry no pics,,not really much to see.

Wednesday, 26 March 2014

update

Not much has happened over the past week, chippies came back on monday to finish internals, the cornice guy also came back and finished the bulk head above the kitchen cabinets,,we are waiting for the tiler to come back and finish a couple of added jobs,and we are also waiting on the painters to come and make a start, was suppose to b happening later this week , cant see it though, he is so far behind the current job hes doing , due to lack of ppl,,,meaning there is only one of him,,so no pics today.

Wednesday, 19 March 2014

Tiling Complete

went to site today, tiler finished,that is until they do under the vanities,,,the portico was rendered today, and the gas line and meter were installed this arvo,,no action on the site now till next week,,here r todays pics






Monday, 17 March 2014

Tiling continues

Productive day,,front porch,feature tiles in both bathrooms,kitchen splashback,laundry splashback,,hoping the white grout in the kitchen looks better then it does now  : all the wall tiles are lined up , ready for tomorrow,,this guy is quick, and a great job to boot,,,our water tank was delivered some time this morning,,here r todays pics




Saturday, 15 March 2014

grouting

Grouting done on the floors in the bathrooms,,black grout,different,,,

Friday, 14 March 2014

Tiling

First day of actually tiling,the tiler will start the walls on monday,,cant wait to see the splashback done,,,hope the porcelin tiles arnt going to b a pain to keep shiney and clean,,only time will tell  lol here  r todays pics